The past two weeks / the next two weeks
• Geoff Goldfinch completed the damp proofing on the day before
read more »
Building Bulletin Number 6---Dated 10 December 2008
The past two weeks
• We have lost some time over the past
read more »
The works the next two weeks
• Externally the concrete foundation works will be completed and the masonry walls will
read more »
The works- the next two weeks
• Foundation works will be completed.
• Concrete work will continue so there will
read more »
Building Bulletin Number 3- Dated 29 October 2008
The works- the next two weeks
• Excavation works will now be
read more »
Building Bulletin Number 2—Dated 15 October 2008
The works - the next two weeks
• The most significant factors over
read more »
BUILDING BULLETIN NUMBER 1 - Dated 1 October 2008
The Works – the next two weeks
• Building work commences
read more »
The internal work to the bar office, wine store, control cupboard and ladies and disabled facilities is coming along nicely.
read more »
Building Project
Position statement at 1 August
Matters have moved on from the notice of 19 July.
Agreement has been
read more »
Report to Members
Building Project - Position statement at 19 July
There have been some fundamental changes to the project
read more »